DBIS RTGS — master plan implementation tracker

Last updated: 2026-04-25
Purpose: Executable tracker mapping the multi-jurisdiction institutional onboarding master plan to DBIS_RTGS_E2E_REQUIREMENTS_MATRIX.md rows and slice-1 scope (SLICE1_SCOPE_FREEZE.md). Status here is documentation of intent; the canonical component status remains the E2E matrix until rows are updated there.

How to use

  1. Pick a workstream below.
  2. Execute engineering / ops tasks until exit criteria match the matrix rows Production gate column.
  3. Update DBIS_RTGS_E2E_REQUIREMENTS_MATRIX.md Current state to Complete (or Retired with rationale).
  4. Link evidence to URA packages per ID-INDONESIA/banking_v1.md where applicable.

Workstream W1 — Canonical OMNL / Fineract rail

Matrix rows (indicative) OMNL / Fineract API rail; Mifos X frontend / tenant
Exit criteria Tenant and operator rail frozen; reproducible posting, office/GL mapping, reconciliation package path.
Owner OMNL / banking ops
URA link SERVER_FUNDS resources get real accountingRef; URA_PILOT_CLOSURE_RUNBOOK.md pilot 2.

Workstream W2 — server-funds-sidecar

Matrix rows server-funds-sidecar (VMID 5803)
Exit criteria Treasury SoR boundaries frozen; draw / hold / release validated with auth; Phoenix SERVER_FUNDS_SIDECAR_URL set in prod.
Owner HYBX integration lead
URA link Pilot 2; UNIVERSAL_RESOURCE_WIRING.md probe returns 200.

Workstream W3 — off-ledger-2-on-ledger-sidecar

Matrix rows Off-ledger → Chain 138 settlement
Exit criteria Canonical event → settlement end-to-end with durable evidence; finality handling closed.
Owner HYBX + Chain 138 settlement lead
URA link settlementOrChainRef in evidence packages.

Workstream W4 — ISO 20022 + institutional 4.995 package

Matrix rows ISO evidence and vault path; Institutional 4.995 package path
Exit criteria --strict or institution-agreed readiness; reproducible archive/hash path.
Owner Regulatory / compliance + eng
Compliance link INDONESIA_PACKAGE_4_995_EVIDENCE_STANDARD.md

Workstream W5 — Indonesia BNI domestic path

Matrix rows Indonesia / BNI domestic banking path
Exit criteria Live endpoint/auth/message contract or explicit deferral documented in matrix + jurisdiction matrix.
Owner Indonesia banking integration lead
Compliance link DBIS_OMNL_INDONESIA_BNI_E2E_INTEGRATION_BLUEPRINT.md

Workstream W6 — Global correspondent path

Matrix rows Global correspondent / liquidity bank path
Exit criteria Same as matrix production gate; cross-border flow validated or out of slice 1.
Owner Cross-border banking integration lead

Workstream W7 — Identity stack (Fabric / Indy / Aries)

Matrix rows Fabric, Indy, Aries, AnonCreds, etc.
Exit criteria Scope decision in/out slice 1; if out, matrix shows Planned/Retired without production claims.
Owner Identity architecture lead

Workstream W8 — Depository / custody / securities

Matrix rows Depository, global custodian, securities-sidecar, custody flow
Exit criteria Canonical lifecycle documented + one path validated or deferred with rationale.
Owner Custody / securities architecture leads
URA link Pilot 1 SKR; policy profile institutional_custody_skr_v1.

Workstream W9 — RTGS production gate

Matrix rows RTGS production gate row
Exit criteria All mandatory rows for chosen architecture = Complete.
Owner DBIS program owner