Action Items - Immediate Next Steps
Date: 2024-11-21
Critical Path (Must Complete First)
1. Monitor UE5 Build ⏳
./scripts/monitoring/ue5_build_monitor.sh
Status: Build in progress (4-6+ hours) Action: Wait for completion, then proceed to step 2
2. Verify UE5 Installation
./scripts/setup/verify_ue5_installation.sh
When: After build completes Action: Verify UnrealEditor binary exists and is correct version
3. Create UE5 Project
./scripts/setup/create_ue5_project.sh
When: After installation verified Action: Creates DubaiMetaverse.uproject
4. Configure Project Settings
When: After project created Action:
- Enable Nanite
- Enable Lumen
- Enable World Partition
- Install required plugins
Parallel Work (Can Do Now)
Data Acquisition ✅ READY
- Research OSM data sources
- Download OSM building data
python3 scripts/data/import_osm_data.py \ --output data/processed/dubai_marina_buildings.geojson \ --bounds "25.07,55.13,25.09,55.15" - Acquire DEM elevation data
- Process data using available scripts
Documentation Review ✅ READY
- Review workflow documentation
- Review asset specifications
- Review system documentation
- Update any outdated references
Asset Planning ✅ READY
- Review asset lists
- Create detailed Cayan Tower specs
- Collect reference images
- Plan asset production pipeline
Script Improvements ✅ READY
- Create common logging function
- Standardize error handling
- Update outdated references
- Add input validation
After UE5 Project Created
Blockout Creation
- Import OSM data to Unreal
- Generate terrain from elevation
- Create building footprints
- Place buildings in level
- Create road network
- Add navigation paths
- Validate scale (1:1)
- Test navigation
Testing & Validation
- Test Nanite mesh import
- Test Lumen lighting
- Test World Partition
- Verify plugins working
- Validate project structure
Project Management
- Set up communication channels
- Schedule weekly reviews
- Verify Git LFS working
- Set up remote repository (if needed)
Priority: Complete critical path first, then parallel work Estimated Time: 1-2 weeks to complete Phase 1